Procurement with Unenforceable Contract Time and the Law of Liquidated Damages


Authors: Cesare Dosi, Michele Moretto
Series: Economy and Society
Editor: Giuseppe Sammarco
Keywords: Public Procurement, Fixed-Price Contracts, Cost Uncertainty, Time Overruns, Liquidated Damages, Real Options
JEL n.: C61, D44, D86, K12

Abstract

Time overruns are common in public works and are not confined to inherently complex tasks. One explanation advanced in this paper is that bidders can undergo unpredictable changes in production costs which generate an option value of waiting. By exploiting the real-option approach, we examine how the inability to force sellers to meet the contract time influences their bidding behaviour, and how this can ultimately affect the parties’ expected payoffs. Further, we examine the outcome of the bidding process when legal rules prevent the promisee from contracting for damage measures which would grant more than her lost expectation. We show that when the pre-agreed compensatory payments prove insufficient to discourage delayed orders, setting a liquidated damages clause would not lead to a Pareto superior outcome with respect to the no-damage-for delay condition. While such a clause would increase the seller’s expected payoff, the buyer’s expected payoff is lower than when the contract does not provide for any compensation for late-delivery.

Download file
Download PDF file

FEEM Newsletter & Update

Subscribe to stay connected.

Your personal data will be processed by Fondazione Eni Enrico Mattei. – data Controller – with the aim of emailing the FEEM newsletter & Update. The use of Your email address is necessary for the implementation of the newsletter service. You are invited to read the Privacy Policy in order to obtain additional information about the protection of Your rights.

This Website uses technical cookies and cookie analytics, as well as “third party” profiling cookies.
If you close this banner or you decide to continue navigating on this Website, you express consent to the use of cookies. If you need additional information or you wish to express selective choices on the use of cookies, please refer to the   Cookie PolicyI agree